Three-point estimates are a project management technique used to define a range of possible outcomes for a particular task or activity by considering three different scenarios: the best-case, worst-case, and most likely estimates. This method allows for a more comprehensive understanding of uncertainty in project planning and scheduling, helping to improve decision-making and resource allocation by taking into account variability and risk.